Xiamen, China · Export worldwide · FOB / CIF / DAP
Bailey truss falsework on spiral welded piles beneath a bridge deck over tidal water
Home / Projects / Haicang Aoguan
Site record · Xiamen, Fujian

Haicang Aoguan Avenue crossing: falsework that stands in the tide

A cast-in-place deck over open water. Everything below it — piles, capping steel, Bailey trusses, deck steel — has to be set, checked and struck from a working platform a few metres above the tide.

LocationAoguan Bay, Haicang, Xiamen StructureCast-in-place deck on falsework ExposureTidal water, salt air StageDeck works, ongoing
What this page is

Four systems, one working level

The crossing is built almost entirely over water, so the temporary works are not a side package — they are the project. Pipe piles carry the load into the seabed, Bailey trusses span between pile bents, ringlock frames give the deck gang a level to work from, and reusable steel forms cast the barrier plinth along each edge.

This page follows the sequence with our own site photographs, from the pile group up to the guardrail post.

01Marine foundation

Spiral welded pipe piles, pile-head steel and capping plates to drawing.

02Bailey falsework

321 / 200 trusses, transoms, sway braces and pins, erected bent by bent.

03Deck works

Reinforcement, kerb and barrier plinth cast on the falsework.

04Barrier

Base-plate guardrail posts and three-tube rail, galvanised for salt air.

01 / Foundation

Piles first, and a cap that can be levelled

Each bent starts with a group of spiral welded pipe piles driven into the bay bed. The pile heads are cut to level and capped with steel that carries the transverse beams — which is where the tolerance of the whole falsework is decided.

The same detail repeats along the crossing, so the capping steel, jacking points and bracing were fabricated as a repeatable set rather than one-off pieces. That is what keeps erection crews moving from bent to bent without waiting on a fitter.

  • Pile-head steel set to the surveyed level, checked before the trusses land
  • Bracing and jacking brackets welded to the same procedure as the caps
  • Galvanised or coated for splash-zone exposure, recorded per bundle
Group of steel pipe piles with capping beams and cross bracing around a pier under construction
Pile group and capping steel at a pier — the level taken off the pile heads.
Looking along the underside of the trestle: steel pipe piles, cross bracing and Bailey trusses over water
Under the deck: pipe piles, bracing and Bailey trusses carry the formwork — the water is the working level below.
Steel pile heads with jacking brackets and capping plates supporting a concrete pier cap
Pile-head jacks and capping plates, set before the trusses are lifted in.
02 / Falsework

Bailey trusses do the spanning, ringlock does the standing

Between the bents, Bailey trusses carry the deck formwork. Along the edge, ringlock frames give the fixing and pouring gang a stable platform with toe boards and edge protection — the part of the package that site crews judge first.

Panels, transoms, sway braces and pins ship as one bill of materials per span, so erection does not stop halfway for a missing pin box.

Bailey trusses and deck formwork on pipe pile bents along a sea crossing
Deck falsework seen from the trestle: trusses on pile bents, formwork on top.
Ringlock falsework and access walkway running along the edge of the bridge deck
Ringlock falsework and the access walkway along the deck edge.
03 / Deck & edge

Where the temporary steel meets the permanent concrete

On top of the falsework the deck is laid out: bearers, soffit formwork, reinforcement, and the edge detail that will eventually hold the barrier. Every one of those interfaces is set out from the same survey line, which is why the kerb, plinth and barrier posts are fabricated to the deck drawing rather than to a catalogue.

The barrier plinth is cast along the deck edge with the anchor bolts set to a template. Posts then land on base plates, shimmed and grouted, with the rail line following the deck curve.

Reinforcement and formwork laid out on the falsework deck, with a crawler crane at the edge
Deck layout on the falsework: bearers, formwork and reinforcement.
Aerial view of the cast deck and barrier line curving along the bay
The cast deck and barrier line, curving with the bay.
Reinforcement and kerb detail at the bridge deck edge
Rebar and drainage kerb before the pour.
Steel guardrail posts on base plates bolted to the cast concrete plinth of a bridge
Barrier posts on base plates, bolted to the cast plinth.
04 / Scale

The crossing reads differently from the air

From the shore the works look like a single line; from above you can see how the trestle, the working platforms and the pile bents step out into the bay, and how much of the site is reached only by the temporary steel itself.

That is the argument for buying the package as one supply: piles, trusses, falsework and edge steel arrive on the same drawings, with the same coating specification and one packing list.

Site footage
The crossing from the air — drone footage along the deck, with the trestle and pile bents in the bay.
Long view of the completed deck line of a sea crossing running along the shore at low tide
The deck line running along the shore, with the falsework struck behind the pour.
Scope of supply

What left the workshop for this site

The table is the package as supplied — not a catalogue list. Dimensions, hole patterns and coating were set against the project drawings and approved before fabrication.

Project sheet
LocationAoguan Bay, Haicang District, Xiamen, Fujian, China
CrossingSea crossing, cast-in-place deck with pedestrian and cycle lane
Foundation steelSpiral welded pipe piles, pile-head steel, capping plates, bracing
Temporary worksBailey 321 / 200 trusses, transoms, sway braces, pins; ringlock falsework
Deck worksReinforcement, kerb steel, cast-in anchor bolts and barrier plinth
BarrierBase-plate guardrail posts, three-tube rail, anchor sets
FinishHot-dip galvanised, with painted elements where specified
DocumentationShop drawings, material certificates, dimensional check, packing list, loading photographs
DeliveryFOB Xiamen / CIF / DAP
Site photography

Twelve frames from the crossing

Unstaged photographs from the deck and the trestle. Click any frame to open it full size.

Request the full set

Photographs from our own site and workshop files, October 2026. Project names describe the works; the supply scope for any particular package is confirmed on the purchase order.

Building over water? Send the drawings.

Tell us the span, the water depth and the port. We reply with an itemised quotation, weights and a preliminary loading plan.

Call WhatsApp Get a quote